July 20, 2016
Room 24 The excavation of the oblong Room 24 completed. The whole surface of the paved floor was uncovered (fig.1). Several building phases can be distinguished. Wall ΙΙΙ, at the […]
July 18, 2016
We began working on the southern half of Quadrant 5 this week, revealing a massive spread of rubble to clean and record.
July 15, 2016
Room 24 The western part of Room 24 was excavated, between Wall I (to the West) and Wall ΙΙ (to the East). A layer of broken schist slabs and coarse […]
June 27, 2016
The team concentrated on completing the first phase of work in the north of Quadrant 5 this week.
June 23, 2016
This week we began work in Quadrant 5, a new excavation area at the eastern side of the Cromlech Tumulus site.
June 21, 2016
We spent our time this week expanding the trench over the Danish Ditch pre-bog field wall to examine a possible terrace and burnt stone feature.
June 17, 2016
The season at the Cromlech Tumulus has begun! We’ll be joined by students from the USA, Australia, Britain, Ireland, India, the Netherlands and Spain.
March 28, 2016
In the final post of her blog series, Lauren Nofi reports on the last week of her internship.